Mitigating Schedule and Cost Overrun Risks in EPC Projects Using Monte Carlo Simulation in Ikeja

Aug 2026 · ABUAD Journal of Engineering Research and Development (AJERD) · 0 citations · 32 references

Abstract

Engineering, Procurement and Construction (EPC) projects play a pivotal role in infrastructure and industrial development in Nigeria but continue to experience significant schedule delays and cost overruns arising from engineering complexity, procurement uncertainty, macroeconomic volatility, and regulatory constraints. This study evaluates the application of Monte Carlo Simulation (MCS) as a probabilistic risk analysis technique for improving the prediction of schedule and cost uncertainties in EPC projects within Ikeja, Lagos State, Nigeria. A quantitative research design was adopted. Primary data were collected from 199 EPC professionals using structured questionnaires, while secondary data were obtained from project schedules, procurement records, cost reports, and risk registers. Descriptive statistics, Kendall's Tau-b correlation, multiple regression analysis, and Monte Carlo Simulation were employed for data analysis at a 5% significance level. Simulation modelling was implemented in Frontline Risk Solver for Microsoft Excel using 10,000 iterations with appropriate probability distributions assigned to project duration and cost variables. The deterministic baseline schedule of 180 days and baseline budget of ₦210 million (2024 price basis) were derived from an actual completed EPC project. The simulation produced a P50 completion duration of 212 days, a P80 duration of 225 days, and only a 35% probability of achieving the deterministic schedule. Sensitivity analysis identified procurement activities, construction duration, imported material costs, inflation, and foreign exchange volatility as the dominant drivers of schedule and cost uncertainty. The findings demonstrate that probabilistic modelling provides more realistic forecasting, supports contingency planning, and improves risk-informed decision-making compared with conventional deterministic planning approaches. The study contributes an integrated framework combining empirical risk assessment, statistical analysis, and Monte Carlo Simulation to improve schedule and cost forecasting in Nigerian EPC projects.

Read PDF

Similar papers

Review Open access Aug 2026

Supply Chain Contingency Estimation: Calculation Methods Towards Better Management of Risk and Cost-Overrun

Contingency estimation methods are largely misapplied in the construction industry and currently align inadequately with risk and cost-overrun. The work discussed here addresses this gap, to present a newly developed structured mechanism to help the project-team choose an appropriate calculation method based upon proje...

Survarna Ananthasivan, A. Whyte, S. Urquhart · 0 citations
Open access Aug 2026

A Risk-Based Decision Framework for Selecting Owner Estimate Percentiles in EPC Projects Using Monte Carlo Simulation and PROMETHEE II

Owner Estimate (OE) determination in Engineering, Procurement, and Construction (EPC) projects remains a challenging process due to high levels of uncertainty arising from technical complexity, market fluctuations, incomplete information, and project-specific risks. Although Monte Carlo Simulation (MCS) can generate pr...

Jannatul Arif, E. Ahyudanari · 0 citations
Open access Sep 2026

Predicting Schedule Delays and Cost Overruns in Iraqi Road and Bridge Projects Using Statistical Analysis and Explainable Artificial Intelligence

An integrated framework that combines statistical analysis, machine learning, and explainable artificial intelligence to identify, rank, and model project-risk factors in Iraqi transport infrastructure supports transparent early-warning assessment of financial, procurement, design, site, and management risks.

Enass Mohammed · 0 citations
Review Open access Sep 2026

Evaluating Risk Management Practices in the Lagos Ibadan Motorway Reconstruction Project

Large-scale infrastructure projects in developing countries remain highly exposed to uncertainty, and inadequate risk management continues to contribute to delays, cost overruns and quality shortfalls. This study evaluates risk management practices on the Lagos–Ibadan Motorway reconstruction project in Nigeria, focusin...

Abiodun Saheed Olaniyan, Odunayo Rofiyat Olaniyan · 0 citations
Open access Aug 2026

Quantifying and Prioritising Construction Delay Risks in Australia Using the Fuzzy Best–Worst Method and a Probability–Impact Matrix

Construction delays remain a persistent challenge in Australian construction projects, contributing to cost escalation, disrupted work sequences, contractual claims, and reduced confidence in project delivery. Although delay causes have been widely investigated, existing studies often provide broad factor lists and pri...

Faranak Zagia, S. Kajewski, S. Omrani et al. · 0 citations
Open access Aug 2026

Sensitivity Analysis of Investment Feasibility Assessments and Monte Carlo Risk Analysis in High-Profile Real Estate Companies

This study aims to analyze the feasibility of investment development using investment analysis methods, including the payback period (PP), Net Present Value (NPV), Internal Rate of Return (IRR), and profitability index, which are part of the capital budgeting method. Furthermore, this study is expected to provide a fra...

Imam Sofyan Lubis, S. Sugiyanto, Zulfitra Zulfitra · 0 citations

We use cookies to run the site and, with your consent, for analytics and to show ads. See our Cookie Policy.