Sep 2026· Journal of Engineering, Design and Technology· 0 citations· 96 references
Abstract
The construction industry has always been plagued by a high number of uncertainties; due to this, cost overruns are the most frequent challenge. To address this problem, this study aims to determine how the presence of risk increases the likelihood of cost overruns and to develop a predictive model that can help reduce them.
The research focuses on designing and evaluating prediction models based on artificial intelligence (AI), trained on 101 data points. Performances were compared based on root mean square error (RMSE), coefficient of determination (R2) and mean absolute percentage error (MAPE). A user-friendly front-end tool was developed to increase the practicality of the study, enabling users to see instant cost overrun predictions. Feature importance for risk events has been conducted to find out the most contributing risk events for the prediction model.
The adaptive neuro fuzzy inference system model outperformed the rest of the AI models with a testing RMSE of 3.4 and an R² of 0.688 and a validation RMSE of 0.35, an R² of 0.96 and an MAPE of 12.5%. Contract-related risk events were found to be most impactful for cost overrun predictions.
This study showed a comparison between various types of AI models. It also developed a graphical user interface, bridging the gap between AI and industry applications. Also found out the important risk factor for cost overruns.
<p>This study proposes an artificial intelligence-based framework for financial risk assessment and cost prediction in construction experiments, focusing on steel hall assembly processes. Construction experiments involving real-time monitoring technologies are associated with significant financial uncertainty. Proposed...
M. Ostojić, M. Knežević· ASES CONGRESS 2026· 0 citations
Accurate shipbuilding cost estimation is important for project quotation, budget preparation, cost control, and operational decision-making. This study proposes an AI-driven hybrid framework for shipbuilding cost estimation by integrating particle swarm optimization (PSO) with the extreme gradient boosting (XGBoost) al...
Yifan Su, Guanghua Xu, Jing Yang· Processes· 0 citations
To support the reduction of energy consumption in steel-making, accurate end-point prediction in steel-making is essential. This prediction enables precise process control, thereby reducing energy and material consumption. Conventional models often lack accuracy or robustness. Their applicability is limited under compl...
Ya-Yun Wang, Sheng-Li Li, Xuan-Peng Song et al.· Metallurgical Research &...· 0 citations
Credit risk assessment of construction contractors is a process that predicts the likelihood of project default by analyzing contractors’ past performance. Existing methods are mostly single-objective and often neglect key project dimensions such as time, quality, and cost, limiting their accuracy and effectiveness. Th...
Nazanin Rahmani, M. Golsorkhtabaramiri, A. Sahafi· Management Strategies and En...· 0 citations
Precision in estimating the contingencies in project parameters has been difficult in Nigeria despite the numerous available computational techniques. This study aims at exploring the predictive ability of artificial neural network with a view of designing prediction models and ascertaining efficiencies. Secondary data...
Momoh Ohiomah Oboirien· Construction Business and Pr...· 0 citations
In the construction industry, cost control, resource inefficiency and schedule delays have been persistent challenges especially in large and complicated projects. The available systems of management are inflexible and do not use real-time data, which leads to sub-optimal decisions. To mitigate the drawbacks, the propo...
Pavankumar Korke, Venkataramana Veeramsetty, G. Shyamala et al.· Sigma Journal of Engineering...· 0 citations
We use cookies to run the site and, with your consent, for analytics and to show ads.
See our Cookie Policy.