Design and Installation of Liner Systems for Heap Leach Facilities with Steeped Slopes
Abstract
The Phase IX heap leach expansion project at a large-scale copper mining operation located in northern Chile was developed to extend the operational life of the hydrometallurgical process between 2024 and 2028, incorporating approximately 200 million tonnes of ore through stacking and secondary leaching. Unlike conventional valley-fill heap leach facilities, the expansion was implemented in a hillside configuration characterized by irregular topography and natural slopes locally exceeding 30% and approaching 50%. Under these conditions, liner stability relies primarily on interface shear behavior, anchorage detailing, and constructability constraints rather than geometric confinement. This paper presents the design and installation of a reinforced geosynthetic liner system consisting of a 2.0 mm textured LLDPE geomembrane, a 400 g/m² nonwoven geotextile, a 5 mm geonet, and localized use of geosynthetic clay liners (GCLs). Material selection was based on interface shear resistance, mechanical protection, and hydraulic performance under steep-slope conditions. The design approach combined laboratory interface testing, numerical evaluation, and project-specific constructability considerations. Field installation was carried out under strict quality control procedures, including phased installation by slope sector, downslope panel alignment, and dedicated anchorage details at crests, toes, and transition zones. Observations during early stacking and initial operational stages indicated stable mechanical and hydraulic performance, with no evidence of slippage, tearing, puncturing, or localized solution accumulation under the applied operational loads. The results highlight the technical feasibility of safely expanding heap leach facilities in topographically constrained environments when liner design, interface behavior, and construction sequencing are addressed in an integrated manner.