Skip to content
Preprint

On Randomized Online Span Minimization

Aug 2026 · 0 citations · 35 references
Computer Science

TL;DR

This work presents a randomized online algorithm with an exact competitive ratio of exactly (1 + e)<3.72, where e is Euler's number, against an oblivious adversary, and shows that no randomized algorithm can have a competitive ratio better than e against an oblivious adversary.

Abstract

We study the online Busy Time scheduling model on a single machine of unbounded capacity, with non-preemptive jobs. In our setting, flexible jobs arrive online with a processing time and deadline, both of which become known to the algorithm at the job's arrival time. The goal is to schedule jobs on the machine to finish all jobs by their deadlines, so that the total time when the machine is turned on (busy time, also called span in this setting) is minimized. We present a randomized online algorithm with an exact competitive ratio of exactly (1 + e)<3.72, where e is Euler's number, against an oblivious adversary, and show that no randomized algorithm can have a competitive ratio better than $e$ against an oblivious adversary. This lower bound holds even for algorithms that are allowed to restart jobs and are given lookahead. Previous work either dealt with special cases, or with deterministic algorithms, for which the known upper bound on the competitive ratio is 5 and the known lower bound is 4. Our findings offer fresh insights into randomization in online energy-aware scheduling. In the setting where jobs have uniform processing times, and a job that is started by the algorithm must be finished, we show that no deterministic algorithm can do better than 2, even when the jobs are agreeable. This deterministic lower bound also holds for uniform processing times and restarts in the scenario where a job's deadline is only revealed at its starting deadline. For Capacitated Busy Time with p_max-lookahead, we obtain a deterministic online algorithm with competitive ratio at most 8 and a randomized online algorithm with competitive ratio at most (4+ e)<6.72, against an oblivious adversary.

View source

Similar papers

Preprint Sep 2026

Busy Time Minimization with Preemption, Migration, and One Resource Requirement

We study the Busy Machine Time with Preemption and Migration and One Resource Requirement problem, motivated by energy minimization in cloud data centers. Given unlimited identical-capacity machines and jobs with release times, deadlines, processing times, and resource requirements, we allow free preemption and migrati...

G. Călinescu, Mozhengfu Liu · 0 citations
Preprint Sep 2026

Better Late Than Never: Online Flow Time Scheduling with Online Estimates

In the classical online flow-time scheduling problem on a single machine, jobs arrive over time and must be processed to minimize the total time they spend in the system: for over fifty years, we have known that SRPT is an optimal online algorithm. But this algorithm requires exactness in two different ways: (a) job si...

Anupam Gupta, Haim Kaplan, Alexander Lindermayr et al. · 0 citations
Preprint Oct 2026

A QPTAS for Stochastic Scheduling of Bernoulli Jobs

We study the classical problem of scheduling jobs with random processing times on $m$ identical machines to minimize the expected sum of completion times, for Bernoulli jobs: job $j$ takes time $p_j$ with probability $q_j$ and time $0$ otherwise, and its outcome is revealed when it starts. The benchmark is an optimal a...

Junho Hwang · 0 citations
Sep 2026

An EPTAS for Vector Scheduling with Time Intervals

We study vector scheduling in which each job is active during a fixed time interval. A job uses several resources and stays on one machine for its entire interval; its resource requirements may depend on the machine. The objective is to minimize the largest resource load over all machines and times. For $r$ machines an...

Junho Hwang · 0 citations
Sep 2026

Scheduling with Mandatory Breaks: NP-Hardness and an Additive-One Approximation

In classical fixed-interval scheduling, each job of a given set must be processed during a prescribed time interval. The goal is to assign each job to exactly one machine such that no two jobs assigned to the same machine overlap in their interiors, and the number of machines used is minimized. Without further constrai...

Shreyas Ghildiyal, N. MuralidharaV · 0 citations
Preprint Oct 2026

Non-Clairvoyant Scheduling is Hard Even for Trees

It is shown that First-In-First-Out (FIFO) has competitive ratio $\Omega(\log m)$ even when every job is an out-tree, and a lower bound is proved of $\Omega(\min\{m,\mathrm{OPT}\})$ for every non-clairvoyant online algorithm, where $\mathrm{OPT}$ is the maximum flow time of an optimal offline schedule.

Kunal Agrawal, Owen Druzgal, M. Prabhu et al. · 0 citations

We use cookies to run the site and, with your consent, for analytics and to show ads. See our Cookie Policy.