Review Open access Sep 2026

Performance Evaluation of the Overhaul Serious Inspection (SE) Project Outcomes for Steam Power Plant Unit 3 at PT XYZ Using a Mixed Methods Approach Based on RII, RCA, & Comparative Analysis

Background: Power plant overhaul projects play a critical role in maintaining project performance targets (quality, cost, and schedule) and operational reliability indicators, including efficiency, Equivalent Availability Factor (EAF), and Equivalent Forced Outage Rate (EFOR). However, many overhaul projects still expe...

Regi Subian Amdriadi, S. Silvianita · 0 citations