This study develops a two-stage scheduling mechanism that integrates Multi-Criteria Decision-Making (MCDM) into the global coordination process and achieves a significantly lower standard deviation than the auction-based mechanism under high resource contention.
Abstract
In engineering R&D organizations, resource contention among autonomous projects creates complex scheduling challenges in distributed multi-project environments. Traditional coordination mechanisms often prioritize global efficiency while overlooking inter-project fairness, which can lead to stakeholder resistance and execution delays. This study proposes a transparent decision support approach for the Distributed Resource-Constrained Multi-Project Scheduling Problem (DRCMPSP). We develop a two-stage scheduling mechanism that integrates Multi-Criteria Decision-Making (MCDM) into the global coordination process. First, an enhanced Chaotic Genetic Algorithm (CGA) with elitism generates local schedules. Second, global resource conflicts are resolved using MCDM methods. Inter-project fairness is implemented by limiting each project’s relative objective deterioration and by evaluating the dispersion of the resulting project-level burdens. Validation through an Unmanned Aerial Vehicle R&D case study and extensive experiments shows that the TOPSIS-based mechanism achieves a significantly lower standard deviation than the auction-based mechanism under high resource contention. The approach supports transparent and fairness-aware conflict resolution by making trade-offs among project-level outcomes explicit to managers.
This study proposes a framework based on Constraint Programming with Boolean Satisfiability (CP-SAT) that links project scheduling to project management decisions by quantifying how individual activities and resource types influence project outcomes through Shapley values. A cooperative game is defined on the chosen mo...
A. Chen, W. Tripiawan· International Journal of Ind...· 0 citations
Existing studies on the Multi-Skill Resource-Constrained Project Scheduling Problem (MS-RCPSP) mostly assume static environments and focus solely on makespan minimization, which does not adequately reflect project scheduling under disruptions. In practice, disruptions may alter task durations during project execution,...
Hao Nguyen Thi, Loc Nguyen The, Huu Dang Quoc· Journal of Data Science and...· 0 citations
Peer-to-peer (P2P) energy trading and shared energy storage (SES) are effective means for multi-microgrid systems to improve operational flexibility, but the cooperative surplus they create must be allocated among participants with heterogeneous carbon responsibilities. However, existing allocation mechanisms determine...
Jian-Jia Tian, Zhi Ye, Ya-Juan Li et al.· Energies· 0 citations
A five-dimensional optimization framework to resolve spatial and resource conflicts in construction scheduling that provides an automated mechanism to secure balanced, mathematically fair schedules, mitigating the operational risks of trade stacking and severe resource peaks.
A. Mohy, Haytham Sanad· Journal of Engineering, Desi...· 0 citations
The management of complex infrastructure projects necessitates the simultaneous optimization of multiple competing objectives beyond the traditional time, cost, and quality triangle. This study proposes a seven-dimensional multiobjective scheduling framework integrating duration, cost, quality, resource leveling, env...
A. Mohy· Journal of construction engi...· 0 citations
Aiming at the vulnerability of nodes within collaborative task execution links and the slow response of link reconfiguration under limited communication conditions and sudden equipment failure scenarios at sea, and noting that existing approaches mainly rely on static optimization or offline planning without an integra...